02/13/2019 |
Application - SUBMITTED |
|
|
02/25/2019 |
Project Review Request
- PRR Routed |
|
03/14/2019 |
Letter Sent - Incomplete letter |
|
04/29/2019 |
Other - Meeting with Applicant |
|
06/17/2019 |
Request for More Info - Via Email |
|
07/24/2019 |
Application - Resubmittal |
|
07/31/2019 |
Project Review Request
- PRR Routed to Building, Public Works, Fire, PD. |
|
08/09/2019 |
Admin Setup - PD PRR Response memo received |
|
10/04/2019 |
Letter Sent - Email to owner with PW trip generation redlines, per request. |
|
10/07/2019 |
Other - TRAFFIC STUDY PROPOSAL AND REQUEST FOR FUNDS SENT TO APPLICANT |
|
10/25/2019 |
Application - Response to PW Redlines submitted |
|
10/28/2019 |
Project Review Request
- Routed to PW only |
|
11/19/2019 |
Letter Sent - Email with redlines on traffic |
|
02/12/2020 |
Other - Provided PD memo to applicant per request |
|
02/19/2020 |
Application - Plans resubmitted |
|
02/24/2020 |
Project Review Request
- PRR Rerouted to Bldg, Fire, PW. Due March 4 |
|
03/13/2020 |
Letter Sent - Incomplete |
|
04/10/2020 |
Application - Plans resubmitted 4/10 |
|
04/20/2020 |
Application - Resubmit description and justification 4/19 |
|
05/21/2020 |
Letter Sent - Complete letter |
|
|