PA2007-073 - Complete Project Chronology
Date | Activity - Status |
04/11/2007 |
Application
- SUBMITTED
|
09/21/2007 |
Environmental
- Notice of Availability/Notice of Completion of a Draft Supplemental Environmental Impact Report published. 45-day comment period begins.
|
11/05/2007 |
Environmental
- Comment period for the Draft SEIR ends.
|
01/31/2008 |
Planning Commission
- Public Hearing conducted - continued
|
02/07/2008 |
Planning Commission
- Public Hearing conducted - continued
|
03/06/2008 |
Planning Commission
- Public hearing scheduled - continued
|
03/20/2008 |
Planning Commission
- Public hearing scheduled
|
04/16/2008 |
City Council
- HEARING CONDUCTED - project approved
adopted Resolution 2008-27, Resolution 2008-28
introduced Ordinance 2008-9, Ordinance 2008-10
|
05/13/2008 |
City Council
- Council adopts Ordinance 2008-09 & 2008-10
|
|