08/20/2007 Application -
09/04/2007 Letter Sent - INCOMPLETE LETTER SENT TO APPLICANT.
04/16/2008 Application - SUBMITTED TENTATIVE MAP APPLICATION
04/29/2008 Project Review Request - Parcel Map and proposed project description has been routed to the necessary departments for review and comments.
06/16/2008 Application - APPLICATION IS INCOMPLETE. LETTER REQUESTING FOR MORE INFORMATION SENT TO APPLICANT.
09/02/2008 Application - requested information sumbmitted by applicant. enviornmental document is being drafted.
11/07/2008 Environmental - MITIGATED NEGATIVE DELCARATION AVAILABLE FRO 20 - DAY PUBLIC REVIEW
12/04/2008 Planning Commission - APPROVED - FORWARD TO CITY COUNCIL
01/27/2009 City Council - Approved. Scheduled for a second reading on 2/10/2009.
02/10/2009 City Council - Second reading APPROVED