PA2007-213 - Complete Project Chronology
DateActivity - Status
10/18/2007 Application -
10/29/2007 Letter Sent - Incomplete letter sent - requesting additional information
10/29/2007 Request for More Info -
03/17/2008 Closed Without Action - INACTIVE LETTER SENT TO APPLICANT
03/25/2008 Application - Reopen application as requested by applicant
05/29/2008 Other - Meeting w/ applicant and architect
06/25/2008 Other - E-mail request from applicant, dated 6-23-08, to place submittal/application on hold while working with Koll.
02/25/2009 Application - DEEMED COMPLETE
05/11/2009 Other - MEETING W/ APPLICANT TO DISCUSS CHANGES TO PROPOSED GPA
06/17/2009 Letter Sent - REQUESTING REVISIONS TO PLANS
06/19/2009 Other - REVISED PLANS AND APPLICATION SUBMITTED
07/14/2009 Request for More Info - PROPOSED SQUARE FOOTAGE REQUIRES REVISION
08/05/2009 Application - COMPLETE - NEW PLANS & PROJECT DESCRIPTION SUBMITTED
08/07/2009 Project Review Request - REVISED PROJECT/PLANS ROUTED
11/09/2009 Environmental - KICK OFF MEETING W/ CONSULTANT
03/18/2010 Letter Sent - TRIBAL CONSULTATION LETTER SENT
05/18/2010 Environmental - 20-DAY PUBLIC REVIEW OF MND 5/18/10 TO 6/710
08/05/2010 Planning Commission - CONTINUED TO 8-19-10
08/19/2010 Planning Commission - PROJECT RECOMMENDED FOR APPROVAL TO CITY COUNCIL
10/21/2010 Other - ALUC FOUND PROJECT TO BE CONSISTENT W/ THE AELUP FOR JWA & HELIPORTS.
02/22/2011 City Council - PUBLIC HEARING - PROJECT APPROVED, ORDINANCE PASS TO 2ND READING ON 3/8/11
03/08/2011 City Council - SECOND READING - ORDINANCE ADOPTED TO AMEND KOLL CENTER NEWPORT PC TEXT