03/14/2008 |
Application
- SUBMITTED
|
04/18/2008 |
Letter Sent
- Application Complete - Initial Study Required
|
04/23/2008 |
Project Review Request
-
|
04/24/2008 |
Environmental
- Request for proposals for environmental consulting sent out
|
12/03/2008 |
Letter Sent
- Received a letter requesting preliminary review of a project alternative.
|
06/11/2009 |
Project Review Request
-
|
07/17/2009 |
Other
- Department comments sent to applicant
|
08/17/2009 |
Project Review Request
- Revised Plans Routed for Department Comments
|
12/14/2009 |
Environmental
- MND IS RELEASED FOR 30-DAY PUBLIC REVIEW
|
01/12/2010 |
Environmental
- MND - END OF 30-DAY PUBLIC REVIEW
|
02/04/2010 |
Planning Commission
- Recommended approval of project as proposed
|
03/09/2010 |
City Council
- Approved
|
12/21/2011 |
Letter Sent
- Extension Granted
|
08/06/2013 |
Letter Sent
- Extension Granted - new expiration date: March 9, 2014
|
05/15/2014 |
Application
- SUBMITTED FOR EXTENSION TO PERMITS
|
05/27/2014 |
Letter Sent
- 1 year extension granted - new expiration date: March 9, 2015
|
|