03/14/2008 Application - SUBMITTED
04/18/2008 Letter Sent - Application Complete - Initial Study Required
04/23/2008 Project Review Request -
04/24/2008 Environmental - Request for proposals for environmental consulting sent out
12/03/2008 Letter Sent - Received a letter requesting preliminary review of a project alternative.
06/11/2009 Project Review Request -
07/17/2009 Other - Department comments sent to applicant
08/17/2009 Project Review Request - Revised Plans Routed for Department Comments
12/14/2009 Environmental - MND IS RELEASED FOR 30-DAY PUBLIC REVIEW
01/12/2010 Environmental - MND - END OF 30-DAY PUBLIC REVIEW
02/04/2010 Planning Commission - Recommended approval of project as proposed
03/09/2010 City Council - Approved
12/21/2011 Letter Sent - Extension Granted
08/06/2013 Letter Sent - Extension Granted - new expiration date: March 9, 2014
05/15/2014 Application - SUBMITTED FOR EXTENSION TO PERMITS
05/27/2014 Letter Sent - 1 year extension granted - new expiration date: March 9, 2015