PA2008-152 - Complete Project Chronology
Date | Activity - Status |
07/28/2008 |
Application
- SUBMITTED
|
08/06/2008 |
Letter Sent
- ADDITIONAL INFORMATION REQUEST TO COMPLETE THE APPLICATION
|
08/06/2008 |
Request for More Info
- APPLICATION DEEMED INCOMPETE
|
10/23/2008 |
Project Review Request
-
|
10/23/2008 |
Application
- DEEMED COMPLETE
|
12/05/2008 |
Letter Sent
-
|
12/05/2008 |
Request for More Info
-
|
01/27/2009 |
City Council
- GENERAL PLAN INITIATION
|
08/11/2009 |
City Council
- Reconsideration of General Plan Amendment Initiation
|
11/25/2009 |
Project Review Request
- Review of revised site plan that includes the additional driveway approach off of PCH.
|
07/01/2010 |
Project Review Request
- Revised site plan showing changes to the access road along PCH
|
07/20/2010 |
Project Review Request
- Revised technical site plan and landscape plan and parking management plan
|
10/07/2010 |
Environmental
- 30-DAY PUBLIC COMMENT ON DRAFT MND BEGIN
|
11/04/2010 |
Environmental
- 30-DAY PUBLIC COMMENT ON DRAFT MND CLOSED
|
06/09/2011 |
Planning Commission
- PLANNING COMMISSION CONTINUED THE APPLICATION TO AUGUST 4TH MEETING
|
08/04/2011 |
Planning Commission
- CONTINUED FROM JUNE 9TH PLANNING COMMISSION MEETING
|
10/20/2011 |
Planning Commission
- CONTINUED FROM AUGUST 4TH PLANNING COMMISSION MEETING
|
11/17/2011 |
Planning Commission
- APPROVED
|
01/24/2012 |
City Council
- APPROVED
|
02/14/2012 |
City Council
- SECOND READING OF ORDINANCE FOR APPROVAL OF DEVELOPMENT AGREEMENT
|
02/28/2012 |
City Council
- SECOND READING FOR THE APPROVAL OF PLANNED COMMUNITY DEVELOPMENT PLAN
|
|