PA2008-152 - Complete Project Chronology
| Date | Activity - Status |
| 07/28/2008 |
Application
- SUBMITTED
|
| 08/06/2008 |
Letter Sent
- ADDITIONAL INFORMATION REQUEST TO COMPLETE THE APPLICATION
|
| 08/06/2008 |
Request for More Info
- APPLICATION DEEMED INCOMPETE
|
| 10/23/2008 |
Project Review Request
-
|
| 10/23/2008 |
Application
- DEEMED COMPLETE
|
| 12/05/2008 |
Letter Sent
-
|
| 12/05/2008 |
Request for More Info
-
|
| 01/27/2009 |
City Council
- GENERAL PLAN INITIATION
|
| 08/11/2009 |
City Council
- Reconsideration of General Plan Amendment Initiation
|
| 11/25/2009 |
Project Review Request
- Review of revised site plan that includes the additional driveway approach off of PCH.
|
| 07/01/2010 |
Project Review Request
- Revised site plan showing changes to the access road along PCH
|
| 07/20/2010 |
Project Review Request
- Revised technical site plan and landscape plan and parking management plan
|
| 10/07/2010 |
Environmental
- 30-DAY PUBLIC COMMENT ON DRAFT MND BEGIN
|
| 11/04/2010 |
Environmental
- 30-DAY PUBLIC COMMENT ON DRAFT MND CLOSED
|
| 06/09/2011 |
Planning Commission
- PLANNING COMMISSION CONTINUED THE APPLICATION TO AUGUST 4TH MEETING
|
| 08/04/2011 |
Planning Commission
- CONTINUED FROM JUNE 9TH PLANNING COMMISSION MEETING
|
| 10/20/2011 |
Planning Commission
- CONTINUED FROM AUGUST 4TH PLANNING COMMISSION MEETING
|
| 11/17/2011 |
Planning Commission
- APPROVED
|
| 01/24/2012 |
City Council
- APPROVED
|
| 02/14/2012 |
City Council
- SECOND READING OF ORDINANCE FOR APPROVAL OF DEVELOPMENT AGREEMENT
|
| 02/28/2012 |
City Council
- SECOND READING FOR THE APPROVAL OF PLANNED COMMUNITY DEVELOPMENT PLAN
|
|