PA2009-067 - Complete Project Chronology
| Date | Activity - Status |
| 04/24/2009 |
APPLICATION
- SUBMITTED
|
| 05/05/2009 |
Letter Sent
- INCOMPLETE LETTER SENT
|
| 06/18/2009 |
Letter Sent
- COMPLETE LETTER SENT
|
| 06/25/2009 |
Environmental
- ENVIRONEMENTAL DETERMINATION MADE, NEGATIVE DECLARATION REQUIRED FOR THIS PROJECT
|
| 07/15/2009 |
Environmental
- REQUEST FOR PROPOSALS SENT TO ENVIRONMENTAL CONSULTANTS FOR NEGATIVE DECLARATION
|
| 08/05/2009 |
Environmental
- DUE DATE FOR ENVIRONMENTAL CONSULTANTS TO SUBMIT PROPOSALS FOR NEGATIVE DECLRATION
|
| 10/21/2009 |
Environmental
- CONSULTANT SELECTED, PROFESSIONAL SERVICES AGREEMENT COMPLETED
|
| 10/30/2009 |
Environmental
- KICKOFF MEETING WITH CONSULTANT SCHEDULED FOR NEGATIVE DECLARATION
|
| 11/25/2009 |
Environmental
- FIRST DRAFT NEGATIVE DECLARATION RECIEVED FROM CONSULTANT FOR STAFF REVIEW AND COMMENT
|
| 12/09/2009 |
Environmental
- STAFF REVIEW AND COMMENT DUE BACK TO CONSULTANT
|
| 01/12/2010 |
Environmental
- NEGATIVE DECLARATION SCHEDULED FOR START OF 30-DAY COMMENT PERIOD
|
| 02/10/2010 |
Letter Sent
- SB18 LETTERS SENT TO NATIVE AMERICAN CONTACTS, START OF 90-DAY REQUEST TO CONSULT PERIOD
|
| 02/10/2010 |
Environmental
- NEGATIVE DECLARATION SCHEDULED FOR END OF 30-DAY COMMENT PERIOD
|
| 03/04/2010 |
Planning Commission
- RECOMMENDED APPROVAL TO CITY COUNCIL
|
| 05/11/2010 |
Other
- END OF SB18 90-DAY REQUEST TO CONSULT PERIOD
|
| 05/25/2010 |
City Council
- APPROVED - WAITING ON COASTAL COMMISSION APPROVAL
|
| 09/28/2010 |
Letter Sent
- LETTER SENT TO COASTAL COMMISSION REQUESTING MEETING FOR LCP AMENDMENT
|
| 06/15/2011 |
Other
- COASTAL COMMISSION APPROVED LCP-NB-MAJ-1O
|
| 07/12/2011 |
City Council
- CITY COUNCIL AFFIRMED COASTAL COMMISION APPROVAL OF CLUP AMENDMENT, CONSENT CALENDAR
|
| 09/28/2011 |
Other
- CALIFORNIA COASTAL COMMISSION FINAL APPROVAL LETTER RECEIVED
|
|