PA2010-114 - Complete Project Chronology
Date | Activity - Status |
08/09/2010 |
Application
- SUBMITTED
|
08/26/2010 |
Project Review Request
-
|
09/02/2010 |
Letter Sent
- Request for Proposals for Env Services
|
10/04/2010 |
Letter Sent
- Request for more information sent to applicant
|
10/20/2010 |
Letter Sent
- Tribal Consultation Letters Mailed Out
|
11/18/2010 |
Project Review Request
- Revised Application Routed for Review
|
11/18/2010 |
Application
- Revised Application Submitted
|
04/11/2011 |
Environmental
- Notice of Intent to Adopt Mitigated Negative Declaration released for 30-day public review period
|
05/11/2011 |
Environmental
- Public Review Period Ends at 5:00 PM
|
06/23/2011 |
Planning Commission
- Denied
|
07/01/2011 |
Appeal Filed - City Council
-
|
08/09/2011 |
City Council
- Project Approved/Ordinance Introduced
|
09/13/2011 |
City Council
- 2nd Reading of Ordinance- Approved
|
06/07/2012 |
Planning Commission
- Architectural and Landscape Review- Approved
|
02/07/2013 |
Planning Commission
- Hearing Date- Substantial Conformance Review of Proposed Revisions- Approved
|
|