PA2011-216 - Complete Project Chronology
DateActivity - Status
12/16/2011 Application - SUBMITTED
01/13/2012 Letter Sent - Incomplete
02/10/2012 Letter Sent - Tribal Consultation List Request sent to Native American Heritage Commission
02/13/2012 Letter Sent - Tribal Consultation Invitations Sent
03/01/2012 Letter Sent - Request For Proposals sent out for environmental documentation
03/09/2012 Application - Lot Line Adjustment and revised project description submitted
04/09/2012 Letter Sent - Incomplete Letter
04/24/2012 City Council - Approved- Professional Service Agreement with PCR for environmental consulting
06/05/2012 Application - Revised PC Development Plan Submitted
06/26/2012 Application - Revised Project Description Submitted
06/29/2012 Project Review Request -
08/14/2012 Application - Revised Project Description Submitted
10/17/2012 Other - Scoping Meeting for the Draft Environmental Impact Report
10/25/2012 Letter Sent - Request for Information
01/16/2013 Application - Application for Development Agreement withdrawn. Affordable Housing Implementation Plan submitted.
07/16/2013 Application - Revised Project Description and PCDP submitted
09/26/2013 Environmental - Environmental Quality Affairs Committee Meeting
10/04/2013 Environmental - Draft EIR released for 45 day public review period
11/07/2013 Planning Commission - Study Session
11/13/2013 Other - Harbor Commission Meeting
11/14/2013 Other - Environmental Quality Affairs Committee Meeting
11/18/2013 Environmental - Draft EIR Public Review Period Ends
12/19/2013 Planning Commission - Recommended Approval
12/23/2013 Letter Sent - ALUC Submittal
01/17/2014 Other - Airport Land Use Commission- Determination of Consistency
02/11/2014 City Council - Approved
02/25/2014 City Council - 2nd Reading of Ordinances
07/11/2014 Application - Coastal Land Use Plan Amendment Request Submitted to Coastal Commission
07/28/2014 Other - Incomplete Letter Received from Coastal Commission Staff
10/09/2014 Other - Response to Coastal Commission Incomplete Letter Sent Out
10/24/2014 Other - Received Letter from Coastal Commission Deeming Application Complete
11/26/2014 Other - Request to Extend time limit on LCP Amendment Request No. LCP-5-NPB-14-0820-2 for Commission Action at December 10-12 meeting in Monterey.
11/03/2015 Letter Sent - Proposed Modifications to CLUP Amendment sent to Coastal Commission
02/10/2016 Application - Revised Lot Line Adjustment Exhibit Submitted
03/17/2016 Planning Commission - Tentively Scheduled- Coastal Commission Modifications
04/12/2016 City Council - Approved
04/26/2016 City Council - 2nd Reading or Ordinances