| Date | Activity - Status |
| 07/12/2012 |
Application
- SUBMITTED
|
| 08/15/2012 |
Letter Sent
- DEEMED INCOMPLETE
|
| 08/23/2012 |
Letter Sent
- TRIBAL CONSULATION REQUEST SENT. 90 DAY DEADLINE FOR COMMENTS IS NOVEMBER 21, 2012.
|
| 12/27/2012 |
Other
- WQMP ROUTED TO BUILDING FOR REVIEW
|
| 02/28/2013 |
Application Complete
- DEEMED COMPLETE LETTER SENT
|
| 09/05/2013 |
Planning Commission
- REMOVED FROM CALENDAR
|
| 12/19/2013 |
Planning Commission
- STUDY SESSION
|
| 01/23/2014 |
Planning Commission
- RECOMMENDED CITY COUNCIL APPROVAL
|
| 02/25/2014 |
City Council
- APPROVED
|
| 03/11/2014 |
City Council
- SECOND READING OF ORDINANCE NO. 2014-06
|
|