| Date | Activity - Status |
| 10/24/2012 |
Application
- SUBMITTED
|
| 11/21/2012 |
Project Review Request
- PRR ROUTED, COMMENTS DUE BACK
|
| 11/21/2012 |
Letter Sent
- INCOMPLETE LTR SENT
|
| 12/06/2012 |
Project Review Request
- PRR ROUTED TO GENERAL SERVICES REGARDING TRASH SERVICE, COMMENTS DUE BACK 12/21/12
|
| 01/07/2013 |
Application
- ADDITIONAL APPLICATION MATERIALS RECEIVED
|
| 01/18/2013 |
Other
- CORRESPONDENCE WITH APPLICANT, PROJECT SCOPE TO BE REVISED TO 23 UNITS FROM 24 UNITS
|
| 01/30/2013 |
Letter Sent
- TRIBAL CONSULTATION LETTERS SENT, 90 DAY CONSULTATION PERIOD ENDS APRIL 30, 2013
|
| 02/19/2013 |
Environmental
- RFP'S FOR CEQA ANALYSIS SENT
|
| 02/26/2013 |
Application
- REVISED PLANS SUBMITTED
|
| 03/04/2013 |
Project Review Request
- SECOND PRR ROUTED, COMMENTS DUE BACK 03/18/2013
|
| 03/04/2013 |
Application
- TRACT MAP AND REVISED WQMP SUBMITTED. WQMP ROUTED TO BAGAHI FOR REVIEW.
|
| 04/02/2013 |
Environmental
- CEQA CONSULTANT SELECTED
|
| 04/04/2013 |
Letter Sent
- INCOMPLETE LTR 2 SENT
|
| 05/22/2013 |
Environmental
- FIRST DRAFT MND RECEIVED FOR CITY REVIEW AND COMMENT, COMMENTS DUE BACK JUNE 6, 2013 TO CONSULTANT
|
| 06/17/2013 |
Environmental
- SECOND DRAFT MND RECEIVED FOR CITY REVIEW AND COMMENT FROM CONSULTANT
|
| 07/12/2013 |
Environmental
- PUBLIC COMMENT PERIOD FOR MND BEGINS
|
| 07/15/2013 |
Environmental
- OPR PUBLIC COMMENT PERIOD BEGINS, REVIEW PERIOD ENDS AUGUST 14, 2013
|
| 08/06/2013 |
Letter Sent
- ADDITIONAL TRIBAL CONSULTATION LETTERS SENT, 90 DAY CONSULTATION PERIOD ENDS NOVEMBER 4, 2013
|
| 08/13/2013 |
Environmental
- END OF MND PUBLIC COMMENT PERIOD
|
| 08/20/2013 |
Letter Sent
- SEVEN ADDITIONAL NAHC CONTACTS CONTACTED WITH REQUEST FOR SHORTENED CONSULTATION PERIOD OF 45-DAYS TO SEPTEMBER 20TH
|
| 08/20/2013 |
Other
- TRIBAL CONTACTS CONTACTED FOR FOLLOW-UP REGARDING INVITATION TO CONSULT IN COMPLIANCE WITH SB18 REQUIREMENTS
|
| 08/22/2013 |
Planning Commission
- CONTINUED
|
| 09/05/2013 |
Planning Commission
- APPROVED, CONTINUED FROM 08/22/13
|
| 09/25/2013 |
Other
- TRIBAL CONTACTS CONTACTED FOR FOLLOW-UP REGARDING INVITATION TO CONSULT IN COMPLIANCE WITH SB18
|
| 11/04/2013 |
Other
- END OF SB18 TRIBAL CONSULTATION PERIOD
|
| 11/12/2013 |
City Council
- APPROVED
|
| 11/13/2013 |
Environmental
- NOD FILED AT COUNTY RECORDERS OFFICE
|
| 11/25/2013 |
Other
- COASTAL CLUP APPLICATION MAILED
|
| 11/26/2013 |
City Council
- ORDINANCE SECOND READING, APPROVED
|
| 12/10/2013 |
Other
- COASTAL COMMISSION COMMENTS RECEIVED
|
| 12/13/2013 |
Other
- COASTAL RESUBMITTAL HAND DELIVERED TO CCC OFFICES
|
| 12/20/2013 |
Other
- COASTAL COMMISSION COMMENTS RECEIVED
|
| 03/12/2014 |
Other
- CLUP AMENDMENT APPROVED AT COASTAL COMMISISON
|
| 04/23/2014 |
Other
- CDP APPLICATION FOR THE PROJECT SUBMITTED TO CALIFORNIA COASTAL COMMISSION
|
| 03/02/2017 |
Application
- EXTENSION OF TIME
|