PA2015-210 - Complete Project Chronology
Date | Activity - Status |
11/23/2015 |
Application
- SUBMITTED
|
11/23/2015 |
Admin Setup
-
|
12/08/2015 |
Project Review Request
- ROUTED TO BUILDING, PUBLIC WORKS/UTILITIES, AND FIRE.
|
12/23/2015 |
Project Review Request
- RETURNED
|
12/23/2015 |
Request for More Info
- REQUESTED ADDITIONAL INFORMATION FROM APPLICANT (WQMP, GRADING, ETC.)
|
01/07/2016 |
Letter Sent
- RFP RELEASED FOR ENVIRONMENTAL CONSULTANT
|
01/25/2016 |
Letter Sent
- RFP DEADLINE REVISED DUE TO RETURNED MAILINGS
|
02/12/2016 |
Other
- PROPOSAL RECEIVED AND UNDER REVIEW
|
03/01/2016 |
Other
- BONTERRA PSOMAS SELECTED AS CEQA CONSULTANT
|
03/16/2016 |
Project Review Request
- PRELIMINARY WQMP ROUTED FOR REVIEW
|
04/04/2016 |
Project Review Request
- PRELIMINARY WQMP - CORRECTIONS RECEIVED
|
04/20/2016 |
Project Review Request
- REVISED PRELIMINARY WQMP ROUTED FOR REVIEW
|
05/16/2016 |
Project Review Request
- PRELIMINARY WQMP 2ND CORRECTIONS RECEIVED
|
05/17/2016 |
Project Review Request
- REVISED PRELIMINARY WQMP ROUTED FOR REVIEW
|
07/22/2016 |
Environmental
- NOTICE OF PREPARATION RELEASED - 30-DAY PERIOD TO CONCLUDE ON AUGUST 22, 2016
|
05/26/2017 |
Letter Sent
- LETTER SENT TO APPLICANT'S REPRESENTATIVES REGARDING CURRENT STATUS AND NECESSARY ITEMS TO PROCEED
|
10/13/2017 |
Application
- REVISED PROJECT PLANS SUBMITTED FOR REVIEW.
|
06/15/2018 |
Application
- WQMP
|
09/13/2018 |
Planning Commission
- Scheduled
|
12/06/2018 |
Planning Commission
- VOTED 6-0 TO RECOMMEND THE CITY COUNCIL CERTIFY THE EIR AND APPROVE THE PROJECT
|
02/12/2019 |
City Council
- VOTED 5-1 TO APPROVE THE PROJECT.
|
02/26/2019 |
City Council
- SECOND READING SCHEDULED.
|
|