PA2015-210 - Complete Project Chronology
DateActivity - Status
11/23/2015 Application - SUBMITTED
11/23/2015 Admin Setup -
12/08/2015 Project Review Request - ROUTED TO BUILDING, PUBLIC WORKS/UTILITIES, AND FIRE.
12/23/2015 Project Review Request - RETURNED
12/23/2015 Request for More Info - REQUESTED ADDITIONAL INFORMATION FROM APPLICANT (WQMP, GRADING, ETC.)
01/07/2016 Letter Sent - RFP RELEASED FOR ENVIRONMENTAL CONSULTANT
01/25/2016 Letter Sent - RFP DEADLINE REVISED DUE TO RETURNED MAILINGS
02/12/2016 Other - PROPOSAL RECEIVED AND UNDER REVIEW
03/01/2016 Other - BONTERRA PSOMAS SELECTED AS CEQA CONSULTANT
03/16/2016 Project Review Request - PRELIMINARY WQMP ROUTED FOR REVIEW
04/04/2016 Project Review Request - PRELIMINARY WQMP - CORRECTIONS RECEIVED
04/20/2016 Project Review Request - REVISED PRELIMINARY WQMP ROUTED FOR REVIEW
05/16/2016 Project Review Request - PRELIMINARY WQMP 2ND CORRECTIONS RECEIVED
05/17/2016 Project Review Request - REVISED PRELIMINARY WQMP ROUTED FOR REVIEW
07/22/2016 Environmental - NOTICE OF PREPARATION RELEASED - 30-DAY PERIOD TO CONCLUDE ON AUGUST 22, 2016
05/26/2017 Letter Sent - LETTER SENT TO APPLICANT'S REPRESENTATIVES REGARDING CURRENT STATUS AND NECESSARY ITEMS TO PROCEED
10/13/2017 Application - REVISED PROJECT PLANS SUBMITTED FOR REVIEW.
06/15/2018 Application - WQMP
09/13/2018 Planning Commission - Scheduled
12/06/2018 Planning Commission - VOTED 6-0 TO RECOMMEND THE CITY COUNCIL CERTIFY THE EIR AND APPROVE THE PROJECT
02/12/2019 City Council - VOTED 5-1 TO APPROVE THE PROJECT.
02/26/2019 City Council - SECOND READING SCHEDULED.