PA2016-127 - Complete Project Chronology
Date | Activity - Status |
07/11/2016 |
Application
- SUBMITTED
|
07/13/2016 |
Admin Setup
-
|
07/20/2016 |
Letter Sent
- APPLICATION INCOMPLETE
|
08/03/2016 |
Application Complete
-
|
09/20/2016 |
Environmental
- NEGATIVE DECLARATION PUBLIC REVIEW PERIOD:
09/20/16 TO 10/20/16
|
10/20/2016 |
Planning Commission
- APPROVAL RECOMMENDED
|
11/22/2016 |
City Council
- APPROVED
|
12/13/2016 |
City Council
- SECOND READING
|
12/16/2016 |
Other
- LC2016-002 submitted to California Coastal Commission
|
12/23/2016 |
Other
- RESUBMITTAL REQUIRED FOR LC2016-002
|
02/07/2017 |
Other
- LC2016-002 RESUBMITTED TO CALIFORNIA COASTAL COMMISSION
|
02/22/2017 |
Withdrawn By Applicant
- TO BE RESUBMITTED
|
06/08/2017 |
Other
- LC2016-002 RESUBMITTED TO CALIFORNIA COASTAL COMMISSION
|
06/23/2017 |
Application Complete
- COASTAL COMMISSION DEEMS APPLICATION COMPLETE
|
08/09/2017 |
Other
- CALIFORNIA COASTAL COMMISSION PUBLIC HEARING - APPROVED
|
|