PA2017-253 - Complete Project Chronology
DateActivity - Status
12/04/2017 Application - SUBMITTED
12/05/2017 Admin Setup -
12/21/2017 Letter Sent - INCOMPLETE LTR SENT BY JWC
01/02/2018 Project Review Request - PRR ROUTED, COMMENTS DUE BACK 01/16/18
01/17/2018 Other - CDP NOTICE OF FILING POSTED ON-SITE
03/08/2018 Application - TRIP GENERATION ASSESSMENT INFORMATION RECEIVED FROM APPLICANT
03/12/2018 Letter Sent - FOLLOW-UP INCOMPLETE LETTER DISTRIBUTED TO THE APPLICANT AT MEETING
03/15/2018 Application - REVISED APPLICATION MATERIALS RECEIVED FROM PROJECT ENGINEER
04/04/2018 Application - SEWER/WATER GENERATION ANALYSIS RECEIVED
05/01/2018 Application - MEETING WITH PROJECT APPLICANT TO DISCUSS SCOPE OF PROJECT
05/04/2018 Letter Sent - INCOMPLETE LTR 3 SENT
11/20/2018 Application - REVISED PROJECT PLANS SUBMITTED
11/26/2018 Project Review Request - PRR ROUTED TO BLDG, LIFE SAFETY, PW, UTILITIES, GENERAL SERVICES, PD, AND HARBOR, COMMENTS DUE BACK 12/10/18
12/20/2018 Letter Sent - INCOMPLETE LTR SENT
03/21/2019 Environmental - RFP SENT, PROPOSALS DUE BACK 05-06-19
09/24/2019 City Council - EIR CONTRACT DATE APPROVED BY CITY COUNCIL, PSOMAS SELECTED, KIMLEY-HORN AS TRAFFIC SUB-CONSULTANT
10/15/2019 Project Review Request - PRR ROUTED, COMMENTS DUE BACK 11-01-2019
10/30/2019 Letter Sent - INCOMPLETE LETTER 5 SENT
11/08/2019 Environmental - 31-DAY NOP RELEASE SCHEDULED 11-08-2019 TO 12-09-2019
11/20/2019 Environmental - NOP SCOPING MEETING DATE
06/11/2020 Environmental - AB-52 consultation requests sent.
07/16/2020 Other - Applicant resubmitted.
09/03/2020 Other - Dept Responses Sent to Applicant - BLDG, FIRE, MOD, REC
09/08/2020 Other - Remaining EIR deposit provided.
09/09/2020 Letter Sent - Incomplete Letter Sent to applicant
09/30/2021 Other - Applicant reviewing comments from departments and considering changes to project.
03/01/2022 Withdrawn By Applicant -