PA2018-185 - Complete Project Chronology
DateActivity - Status
08/08/2018 Application -
08/15/2018 Project Review Request - PRR ROUTED, COMMENTS DUE BACK 09/05/2018
09/06/2018 Letter Sent - INCOMPLETE LTR SENT
09/10/2018 Project Review Request - PRR ROUTED TO FIRE SERVICES, PD, AND MOD, COMMENTS DUE BACK SEPTEMBER 21
09/11/2018 Admin Setup -
09/20/2018 Project Review Request - PRR ROUTED TO UTILITIES, COMMENTS DUE BACK OCTOBER 4
12/21/2018 Application - APPLICATION MATERIALS RESUBMITTED
12/21/2018 Environmental - PLACEWORKS CEQA PROJECT DESCRIPTION SUBMITTED TO CITY
01/29/2019 Project Review Request - PRR ROUTED, COMMENTS DUE BACK 02/13/19
01/31/2019 Environmental - CEQA COMMENTS ON PROJECT DESCRIPTION SENT TO CONSULTANT
02/04/2019 Letter Sent - INCOMPLETE LTR 2 SENT
03/20/2019 Letter Sent - NAHC REQUEST LETTER SENT
04/04/2019 Letter Sent - SB-18 LETTERS SENT, 90-DAY NOTICE PERIOD THROUGH 07/03/19 AB-52 LETTERS SENT, 30-DAY NOTICE PERIOD THROUGH 05/04/19
04/09/2019 Other - REQUEST TO CONSULT RECEIVED PER AB-52
04/16/2019 Application - APPLICATION MATERIALS RESUBMITTED
04/18/2019 Planning Commission - PC STUDY SESSION
04/23/2019 Project Review Request - PRR ROUTED, COMMENTS DUE BACK 05-03-19
05/21/2019 Environmental - SECOND DRAFT ADDENDUM RECEIVED FROM PLACEWORKS
06/05/2019 Application - APPLICATION MATERIALS RESUBMITTED
06/17/2019 Environmental - SECOND DRAFT EIR ADDENDUM COMMENTS PROVIDED TO PLACEWORKS
06/26/2019 Application Complete -
06/28/2019 Other - ALUC APPLICATION SUBMITTED
07/08/2019 Environmental - FINAL EIR ADDENDUM RECIEVED FROM PLACEWORKS
07/18/2019 Planning Commission - PC RECOMMENDED CITY COUNCIL CERTIFICATION OF EIR ADDENDUM AND APPROVAL OF PROJECT
07/18/2019 Other - ALUC APPROVED
08/13/2019 City Council - CITY COUNCIL APPROVED
09/10/2019 City Council - CITY COUNCIL ORDINANCES SECOND READING SCHEDULED