PA2019-027 - Complete Project Chronology
DateActivity - Status
02/13/2019 Application - SUBMITTED
02/21/2019 Admin Setup -
02/25/2019 Project Review Request - PRR Routed
03/14/2019 Letter Sent - Incomplete letter
04/29/2019 Other - Meeting with Applicant
06/17/2019 Request for More Info - Via Email
07/24/2019 Application - Resubmittal
07/31/2019 Project Review Request - PRR Routed to Building, Public Works, Fire, PD.
08/09/2019 Admin Setup - PD PRR Response memo received
10/04/2019 Letter Sent - Email to owner with PW trip generation redlines, per request.
10/07/2019 Other - TRAFFIC STUDY PROPOSAL AND REQUEST FOR FUNDS SENT TO APPLICANT
10/25/2019 Application - Response to PW Redlines submitted
10/28/2019 Project Review Request - Routed to PW only
11/19/2019 Letter Sent - Email with redlines on traffic
02/12/2020 Other - Provided PD memo to applicant per request
02/19/2020 Application - Plans resubmitted
02/24/2020 Project Review Request - PRR Rerouted to Bldg, Fire, PW. Due March 4
03/13/2020 Letter Sent - Incomplete
04/10/2020 Application - Plans resubmitted 4/10
04/20/2020 Application - Resubmit description and justification 4/19
05/21/2020 Letter Sent - Complete letter
08/20/2020 Planning Commission - MEETING CANCELED
10/07/2021 Planning Commission - APPROVED
11/17/2021 Notice of Final Action -