PA2019-124 - Complete Project Chronology
| Date | Activity - Status |
| 09/12/2019 |
Other
- MEETING WITH PUBLIC WORKS TO DISCUSS DEPARTMENT FEEDBACK ON INITIAL CONCEPT PLANS
|
| 11/04/2019 |
Other
- JUNIOR LIFEGUARD MEETING WITH PUBLIC WORKS
|
| 10/06/2020 |
Administrative Action
- PB&R COMMISSION REVIEW OF PROJECT, RECOMMENDED APPROVAL, CEQA DETERMINATION STILL PENDING RECEIPT OF SUPPORTING STUDIES
|
| 03/09/2021 |
City Council
- CITY COUNCIL DESIGN APPROVAL, TITLE 20 WAIVER, AND ADOPTION OF CLASS 32 CEQA EXEMPTION
|
| 06/03/2021 |
Application
- APPLICATION SUBMITTED TO CCC, 5-21-0391
|
| 11/22/2021 |
Application Complete
- CCC CDP APPLICATION DEEMED COMPLETE BY COASTAL
|
| 03/09/2022 |
Other
- CCC - COASTAL DEVELOPMENT PERMIT: 03/09/2022
Approved with Special Conditions: Dated 06/28/2022
|
|