PA2019-128 - Complete Project Chronology
Date | Activity - Status |
06/26/2019 |
Application
- SUBMITTED
|
06/28/2019 |
Project Review Request
- PRR ROUTED, COMMENTS DUE BACK 07/02/2019
|
07/16/2019 |
Admin Setup
-
|
02/06/2020 |
Application
- Application resubmitted.
|
02/12/2020 |
Project Review Request
- Routed to Public Works, Utilities and Real Property - comments requested by February 18, 2020.
|
03/12/2020 |
Application
- Notice of Incomplete Filing transmited to applicant and carrier via email.
|
|