PA2019-154 - Complete Project Chronology
DateActivity - Status
08/22/2019 Planning Commission - APPROVED
10/08/2019 City Council - Approved submittal to Coastal Commission
10/29/2019 Application - LCP Amendment Request Submitted to Coastal Commission
11/15/2019 Application Complete - LCP Amendment Request No. 2-19 (LCP-5-NPB-19-0151-2) Notice of CCC Application Complete Received: Dated 11/15/19 CCC Public Hearing Scheduled for 12/12/2019 requesting one-year extension
12/07/2020 Letter Sent - Withdrew LCP A request to allow more time to collaborate on suggested modifications
04/27/2021 Application - LCP Amendment Application Submitted to Coastal Commission
05/24/2021 Request for More Info - LCP AMENDMENT NO. LCPA-5-NPB-21-0036-1 PART D: CCC REQUEST FOR MORE INFO RECEIVED
05/24/2021 Other - LCP Amendment Application Resubmitted
06/08/2021 Application Complete - LCP AMENDMENT NO. LCPA-5-NPB-21-0036-1 PART D: CCC SUBMITTAL COMPLETE