PA2019-216 - Complete Project Chronology
Date | Activity - Status |
10/22/2019 |
Application
- SUBMITTED
|
11/18/2019 |
Admin Setup
-
|
11/20/2019 |
Letter Sent
- Emailed compete letter to Devin Lucas
|
02/20/2020 |
Planning Commission
- PC adopted Resolution Nos. PC2020-002, PC2020-003, & PC2020-004 to recommend City Council approve project.
|
04/28/2020 |
City Council
- City Council Approved. Pending Coastal Commission review
|
09/29/2020 |
Other
- LCP Amendment Submitted
|
10/13/2020 |
Other
- COASTAL COMMISSION LCP-5-NPB-20-0060-2 (NO. 2-20) - SUBMITTAL DEEMED COMPLETE
|
12/09/2020 |
Other
- SCHEDULED CCC HEARING - REQUEST FOR EXTENSION (LCP-5-NPB-20-0060-2 PART A)
PUBLIC NOTICE DATED 11/23/2020
|
10/13/2021 |
Application Complete
- LCP AMENDMENT NO. LCP-5-NPB-20-0060-2 PART A:
CCC LCP AMENDMENT APPROVED
|
|