PA2019-249 - Complete Project Chronology
DateActivity - Status
12/02/2019 Application - SUBMITTED
12/10/2019 Admin Setup -
06/12/2020 Application - APPLICATION RESUBMITTAL RECEIVED
08/26/2020 Request for More Info - Application deemed incomplete.
09/25/2020 Application - Application resubmitted
10/22/2020 Application - Request for more information - Application deemed Incomplete
11/10/2020 Application - resubmittal received
12/07/2020 Application Deemed Complete -
01/21/2021 Planning Commission - CONTINUED TO 2/18 PC
02/18/2021 Planning Commission - APPROVED
02/22/2021 Appealed - Call for Review to City Council
04/27/2021 City Council - Call for Review/Appeal Hearing -Item continued to 5/25/21 City Council Hearing
05/25/2021 City Council - CONTINUED TO JULY 27, 2021 CITY COUNCIL MEETING
07/27/2021 City Council - APPROVED
08/18/2021 Appeal Filed - Coastal Commission -
08/18/2021 Other - APPEAL PERIOD ENDING: 08/18/2021 (5-NPB-21-0713) Notice of CCC Appeal Period Received: Dated 08/06/2021 Corrected Notice of CCC Appeal Period Received: Dated 08/10/2021
10/13/2021 Other - CALIFORNIA COASTAL COMMISSION DETERMINED NO SUBSTANTIAL ISSUE (A-5-NPB-21-0058)