PA2019-249 - Complete Project Chronology
Date | Activity - Status |
12/02/2019 |
Application
- SUBMITTED
|
12/10/2019 |
Admin Setup
-
|
06/12/2020 |
Application
- APPLICATION RESUBMITTAL RECEIVED
|
08/26/2020 |
Request for More Info
- Application deemed incomplete.
|
09/25/2020 |
Application
- Application resubmitted
|
10/22/2020 |
Application
- Request for more information - Application deemed Incomplete
|
11/10/2020 |
Application
- resubmittal received
|
12/07/2020 |
Application Deemed Complete
-
|
01/21/2021 |
Planning Commission
- CONTINUED TO 2/18 PC
|
02/18/2021 |
Planning Commission
- APPROVED
|
02/22/2021 |
Appealed
- Call for Review to City Council
|
04/27/2021 |
City Council
- Call for Review/Appeal Hearing -Item continued to 5/25/21 City Council Hearing
|
05/25/2021 |
City Council
- CONTINUED TO JULY 27, 2021 CITY COUNCIL MEETING
|
07/27/2021 |
City Council
- APPROVED
|
08/18/2021 |
Appeal Filed - Coastal Commission
-
|
08/18/2021 |
Other
- APPEAL PERIOD ENDING: 08/18/2021 (5-NPB-21-0713)
Notice of CCC Appeal Period Received: Dated 08/06/2021
Corrected Notice of CCC Appeal Period Received: Dated 08/10/2021
|
10/13/2021 |
Other
- CALIFORNIA COASTAL COMMISSION DETERMINED NO SUBSTANTIAL ISSUE (A-5-NPB-21-0058)
|
|