PA2020-020 - Complete Project Chronology
| Date | Activity - Status |
| 02/03/2020 |
Application
- SUBMITTED
|
| 02/20/2020 |
Admin Setup
-
|
| 02/27/2020 |
Letter Sent
- Incomplete Letter Sent to Applicant
|
| 06/23/2020 |
Other
- Applicant Resubmitted Materials
|
| 07/06/2020 |
Other
- Applicant provided CEQA fees
|
| 07/23/2020 |
Letter Sent
- Incomplete Filing Letter sent to applicant
|
| 09/21/2020 |
Follow-up Review
- Applicant resubmitted materials
|
| 10/16/2020 |
Request for More Info
- Requested additional materials. Tech study updates, view sims, digital plans.
|
| 11/30/2020 |
Environmental
- SCOPING MEETING
|
| 12/07/2020 |
Other
- NAHC SB18 Request sent. Follow up sent via email 12/16 and NAHC confirmed receipt of the request.
|
| 12/09/2020 |
Follow-up Review
- Applicant resubmitted materials.
|
| 12/14/2020 |
Application Complete
- Application deemed complete. Letter sent to applicant.
|
| 01/07/2021 |
Environmental
- SB-18 Letters sent to Tribal Governments via certified mail and email.
|
| 02/01/2021 |
Other
- Prelim WQMP Approved by Sergio
|
| 03/11/2021 |
Environmental
- Sent follow up emails regarding SB-18 to Tribal Governments that have not responded.
|
| 04/21/2021 |
Environmental
- Consultation meeting with Tribal Government.
|
| 04/26/2021 |
Other
- Fiscal Analyis to be prepared. Fee paid by applicant.
|
| 04/29/2021 |
Environmental
- NOA Comment Period April 29, 2021, to June 14, 2021
|
| 05/06/2021 |
Planning Commission
- STUDY SESSION
|
| 06/23/2021 |
Application
- Resubmit plans and Circulation Plan (on 6/25/21)
|
| 08/19/2021 |
Planning Commission
- APPROVED - RECCOMMENDED APPROVAL TO CC
|
| 09/28/2021 |
City Council
- APPROVED
|
| 10/01/2021 |
Environmental
- NOD Posted to SCH and County
|
| 10/12/2021 |
City Council
- SECOND READING OF ORDINANCES - APPROVED
|
|