PA2020-020 - Complete Project Chronology
DateActivity - Status
02/03/2020 Application - SUBMITTED
02/20/2020 Admin Setup -
02/27/2020 Letter Sent - Incomplete Letter Sent to Applicant
06/23/2020 Other - Applicant Resubmitted Materials
07/06/2020 Other - Applicant provided CEQA fees
07/23/2020 Letter Sent - Incomplete Filing Letter sent to applicant
09/21/2020 Follow-up Review - Applicant resubmitted materials
10/16/2020 Request for More Info - Requested additional materials. Tech study updates, view sims, digital plans.
11/30/2020 Environmental - SCOPING MEETING
12/07/2020 Other - NAHC SB18 Request sent. Follow up sent via email 12/16 and NAHC confirmed receipt of the request.
12/09/2020 Follow-up Review - Applicant resubmitted materials.
12/14/2020 Application Complete - Application deemed complete. Letter sent to applicant.
01/07/2021 Environmental - SB-18 Letters sent to Tribal Governments via certified mail and email.
02/01/2021 Other - Prelim WQMP Approved by Sergio
03/11/2021 Environmental - Sent follow up emails regarding SB-18 to Tribal Governments that have not responded.
04/21/2021 Environmental - Consultation meeting with Tribal Government.
04/26/2021 Other - Fiscal Analyis to be prepared. Fee paid by applicant.
04/29/2021 Environmental - NOA Comment Period April 29, 2021, to June 14, 2021
05/06/2021 Planning Commission - STUDY SESSION
06/23/2021 Application - Resubmit plans and Circulation Plan (on 6/25/21)
08/19/2021 Planning Commission - APPROVED - RECCOMMENDED APPROVAL TO CC
09/28/2021 City Council - APPROVED
10/01/2021 Environmental - NOD Posted to SCH and County
10/12/2021 City Council - SECOND READING OF ORDINANCES - APPROVED