PA2020-068 - Complete Project Chronology
Date | Activity - Status |
05/13/2020 |
Application
- SUBMITTED
|
06/16/2020 |
Application
- INCOMPLETE - LETTER SENT TO APPLICANT.
|
06/17/2020 |
Admin Setup
-
|
08/07/2020 |
Application
- Resubmittal received.
|
09/23/2020 |
Application
- Deemed incomplete - Letter sent to applicant.
|
10/30/2020 |
Application
- Resubmittal received.
|
11/10/2020 |
Project Review Request
- Routed to Building, Public Works, Fire, and Real Property.
|
02/18/2021 |
Application
- Resubmittal received.
|
03/29/2021 |
Project Review Request
- Routed to Building, Public Works, Fire and Real Property.
|
05/17/2021 |
Application
- Resubmittal received.
|
06/21/2021 |
Project Review Request
- Routed to Building, Public Works, Fire and Real Property.
|
07/20/2021 |
Application
- Resubmittal received.
|
07/21/2021 |
Project Review Request
- Routed to Building and Public Works.
|
|