DateActivity - Status
01/21/2021 Application - SUBMITTED
01/26/2021 Admin Setup -
02/09/2021 Project Review Request - Sent to building, fire, PW, and EMP. Requested date: 2/23/2021 or ASAP.
02/09/2021 Letter Sent - Incomplete letter sent to Applicant.
03/25/2021 Project Review Request - Second round sent to building, PW, and EMP. Requested date: 4/2/2021 or ASAP.
04/15/2021 Zoning Administrator Hearing - CONTINUED TO THE MAY 13, 2021 ZA HEARING.
05/05/2021 Application Complete - Notice of Complete Filing sent to applicant.
05/13/2021 Zoning Administrator Hearing - APPROVED