01/28/2021 Application - SUBMITTED
02/02/2021 Admin Setup -
02/24/2021 Letter Sent - Application deemed incomplete
04/22/2021 Letter Sent - deemed incomplete
05/24/2021 Application Complete - Deemed complete.
06/10/2021 Zoning Administrator Hearing - APPROVED
06/25/2021 Notice of Final Action - sent to CCC
07/16/2021 Other - APPEAL PERIOD ENDING: 07/16/2021 (5-NPB-21-0623) Notice of CCC Appeal Period Received: Dated 07/08/2021