02/12/2021 Application - SUBMITTED
02/16/2021 Admin Setup -
03/09/2021 Letter Sent - Notice of Incomplete Filing Letter sent to applicant.
03/16/2021 Application Complete - Notice of Complete filing letter sent to applicant.
04/15/2021 Zoning Administrator Hearing - APPROVED
04/30/2021 Notice of Final Action -
05/14/2021 Other - APPEAL PERIOD ENDING: 05/14/2021 (5-NPB-21-0422) Notice of CCC Appeal Period Received: Dated 05/07/21 Notice of CCC Final Permit Received: Dated 05/19/21