PA2021-061 - Complete Project Chronology
Date | Activity - Status |
03/17/2021 |
Application
- SUBMITTED
|
03/18/2021 |
Admin Setup
-
|
03/25/2021 |
Project Review Request
- PRR SENT TO PW, BUILDING, FIRE
|
03/29/2021 |
Letter Sent
- incomplete letter sent via email
|
04/19/2021 |
Application
- DOCUMENTS RECEIVED (REQUESTED FROM INCOMPLETE LETTER)
|
05/05/2021 |
Application Complete
- APPLICATION COMPLETE AND LETTER SENT VIA EMAIL
|
06/10/2021 |
Zoning Administrator Hearing
- APPROVED
|
|