PA2021-084 - Complete Project Chronology
Date | Activity - Status |
04/08/2021 |
Application
- SUBMITTED
|
04/14/2021 |
Admin Setup
-
|
04/21/2021 |
Project Review Request
- PRR SENT TO BLDG
|
04/28/2021 |
Project Review Request
- PRR SENT TO PW
|
05/06/2021 |
Letter Sent
- incomplete letter sent via email
|
05/17/2021 |
Application
- SECOND PLAN CHECK RECEIVED ON MAY 14, 2021 (5/14/2021)
|
07/29/2021 |
Zoning Administrator Hearing
- APPROVED
|
08/20/2021 |
Other
- APPEAL PERIOD ENDING: 08/20/2021 (5-NPB-21-0749)
Notice of CCC Appeal Period Received: Dated 08/16/2021
Notice of CCC Final Permit Received: Dated 09/01/2021
|
|