PA2021-099 - Complete Project Chronology
Date | Activity - Status |
04/22/2021 |
Application
-
|
04/26/2021 |
Admin Setup
-
|
03/21/2022 |
Application Complete
-
|
04/21/2022 |
Planning Commission
- APPROVED
|
05/06/2022 |
Notice of Final Action
- Sent to CCC
|
05/11/2022 |
Appeal Filed - Coastal Commission
- APPEAL FILED: 05/11/2022 (A-5-NPB-22-0022)
NOTIFICATION RECEIVED: DATED 05/27/2022
|
05/11/2022 |
Other
- APPEAL: 05/11/2022 (A-5-NPB-22-0022)
CCC - Commission Notification of Appeal Received: Dated 05/27/2022
|
07/13/2022 |
Other
- APPEAL: 07/13/2022 (A-5-NPB-22-0022)
CCC - Commission Notification of Appeal Received: Dated 06/24/2022
|
|