PA2021-120 - Complete Project Chronology
DateActivity - Status
05/25/2021 Application - SUBMITTED
05/26/2021 Admin Setup -
06/02/2021 Project Review Request - routed
06/25/2021 Letter Sent - Incomplete letter
11/15/2021 Application - resubmit
11/18/2021 Project Review Request - Second PRR Routed
07/07/2022 Administrative Action - APPROVED BY CDD