PA2021-120 - Complete Project Chronology
Date | Activity - Status |
05/25/2021 |
Application
- SUBMITTED
|
05/26/2021 |
Admin Setup
-
|
06/02/2021 |
Project Review Request
- routed
|
06/25/2021 |
Letter Sent
- Incomplete letter
|
11/15/2021 |
Application
- resubmit
|
11/18/2021 |
Project Review Request
- Second PRR Routed
|
07/07/2022 |
Administrative Action
- APPROVED BY CDD
|
|