PA2021-146 - Complete Project Chronology
Date | Activity - Status |
06/17/2021 |
Admin Setup
-
|
06/17/2021 |
Application
- SUBMITTED
|
07/27/2021 |
Letter Sent
- Notice of incomplete filing sent to applicant.
|
08/23/2021 |
Application Complete
- Notice of Complete Filing Letter Sent to Applicant.
|
09/30/2021 |
Zoning Administrator Hearing
- APPROVED
|
11/02/2021 |
Other
- APPEAL PERIOD ENDING: 11/02/2021 (5-NPB-21-0960)