PA2021-158 - Complete Project Chronology
Date | Activity - Status |
06/25/2021 |
Application
- SUBMITTED
|
06/29/2021 |
Admin Setup
-
|
11/10/2021 |
Zoning Administrator Hearing
- APPROVED
|
12/15/2021 |
Other
- APPEAL PERIOD ENDING: 12/15/2021 (5-NPB-21-1112)
Notice of CCC Appeal Period Received: Dated 12/08/2021
Notice of CCC Final Permit Received: Dated 12/21/2021
|
|