PA2021-202 - Complete Project Chronology
Date | Activity - Status |
08/06/2021 |
Application
- SUBMITTED
|
08/11/2021 |
Admin Setup
-
|
08/30/2021 |
Project Review Request
- PRR ROUTED TO BLDG, PW, FIRE, CODE ENFORCEMENT, REAL PROPERTY
|
10/21/2021 |
Letter Sent
- NOTICE OF INCOMPLETE FILING SENT VIA EMAIL
|
11/24/2021 |
Zoning Administrator Hearing
- APPROVED
|
12/14/2021 |
Notice of Final Action
- NOFA SENT TO COASTAL
|
12/30/2021 |
Other
- APPEAL PERIOD ENDING: 12/30/2021 (5-NPB-21-1155)
Notice of CCC Appeal Period Received: Dated 12/21/2021
Notice of CCC Final Permit Received: Dated 01/12/2022
|
|