PA2022-011 - Complete Project Chronology
DateActivity - Status
01/10/2022 Application - SUBMITTED
01/12/2022 Admin Setup -
02/09/2022 Letter Sent - Deemed incomplete. Letter sent.
03/09/2022 Other - Applicant resubmitted
03/22/2022 Other - Routed to WQMP, Fire, PW
05/06/2022 Other - applicant resubmitted
05/10/2022 Other - routed to WQMP and PW
06/09/2022 Planning Commission - APPROVED
06/24/2022 Notice of Final Action - SENT VIA EMAIL AND MAIL
07/05/2022 Other - CCC Appeal Period ends 7/11/22