10/29/2007 |
Letter Sent - Incomplete letter sent - requesting additional information |
|
10/29/2007 |
Request for More Info - |
|
03/17/2008 |
Closed Without Action - INACTIVE LETTER SENT TO APPLICANT |
|
03/25/2008 |
Application - Reopen application as requested by applicant |
|
05/29/2008 |
Other - Meeting w/ applicant and architect |
|
06/25/2008 |
Other - E-mail request from applicant, dated 6-23-08, to place submittal/application on hold while working with Koll. |
|
02/25/2009 |
Application - DEEMED COMPLETE |
|
05/11/2009 |
Other - MEETING W/ APPLICANT TO DISCUSS CHANGES TO PROPOSED GPA |
|
06/17/2009 |
Letter Sent - REQUESTING REVISIONS TO PLANS |
|
06/19/2009 |
Other - REVISED PLANS AND APPLICATION SUBMITTED |
|
07/14/2009 |
Request for More Info - PROPOSED SQUARE FOOTAGE REQUIRES REVISION |
|
08/05/2009 |
Application - COMPLETE - NEW PLANS & PROJECT DESCRIPTION SUBMITTED |
|
08/07/2009 |
Project Review Request
- REVISED PROJECT/PLANS ROUTED |
|
11/09/2009 |
Environmental - KICK OFF MEETING W/ CONSULTANT |
|
03/18/2010 |
Letter Sent - TRIBAL CONSULTATION LETTER SENT |
|
05/18/2010 |
Environmental - 20-DAY PUBLIC REVIEW OF MND 5/18/10 TO 6/710 |
|
|
|
10/21/2010 |
Other - ALUC FOUND PROJECT TO BE CONSISTENT W/ THE AELUP FOR JWA & HELIPORTS. |
|
02/22/2011 |
City Council
- PUBLIC HEARING - PROJECT APPROVED, ORDINANCE PASS TO 2ND READING ON 3/8/11 |
|
03/08/2011 |
City Council
- SECOND READING - ORDINANCE ADOPTED TO AMEND KOLL CENTER NEWPORT PC TEXT |
|