PA2012-146    LIDO VILLAS (DART) Council District 1
NT2015-001 - Tentative Tract Map
AIC2014026 - APPROVAL-IN-CONCEPT
AIC2014008 - APPROVAL-IN-CONCEPT
SD2013-001 - Site Development Review
ND2013-001 - Negative Declaration
NT2013-001 - Tentative Tract Map
LC2013-001 - LCP Amendment
CA2012-008 - Code Amendment
GP2012-005 - General Plan Amendment
View Ordinances and Resolutions (Not all projects require a Resolution or Ordinance, or documents may not be available at this time.)
Description: EXTENSION OF TIME FOR TRACT MAP NO. NT2013-001 The applicant requests approval for the development 23 townhouse style multi-family dwelling units. The following approvals are requested or required in order to implement the project as proposed: 1. General Plan Amendment-to change the land use of the property at 3303 Via Lido from PI (Private Institutions) to RM (Multi-Unit Residential). 2. Zoning Code Amendment - to change the zoning designations of the properties at 3303 Via Lido from PI (Private Institutions) and 3355 Via Lido from RM (Multi-Unit Residential) and establish a Planned Community Development Plan (PC-59) over the entire project site with development standards for a new 23 unit townhouse style multi-family units. 3. Coastal Land Use Plan Amendment - to change the land use of the property at 3303 Via Lido from PI-B (Private Institutions) to RM-D (Multi-Unit Residential). 4. Site Development Review - to accommodate the 23 unit multi-family condominium development. 5. Tract Map - to combine six parcels into a single parcel and building site for a 23-unit condominium development. 6. Mitigated Negative Declaration
Contact: M. Nova - 949-644-3249

Status: APPROVED Applied: 10/24/2012 Follow-up Rev: Approved: 11/13/2013
Final: Effective: 11/27/2013 Expired: Denied:
Pending: Date Withdrawn: Voided:
Date Activity - Status
10/24/2012 Application - SUBMITTED
11/21/2012 Project Review Request - PRR ROUTED, COMMENTS DUE BACK
11/21/2012 Letter Sent - INCOMPLETE LTR SENT
12/06/2012 Project Review Request - PRR ROUTED TO GENERAL SERVICES REGARDING TRASH SERVICE, COMMENTS DUE BACK 12/21/12
01/07/2013 Application - ADDITIONAL APPLICATION MATERIALS RECEIVED
01/18/2013 Other - CORRESPONDENCE WITH APPLICANT, PROJECT SCOPE TO BE REVISED TO 23 UNITS FROM 24 UNITS
01/30/2013 Letter Sent - TRIBAL CONSULTATION LETTERS SENT, 90 DAY CONSULTATION PERIOD ENDS APRIL 30, 2013
02/19/2013 Environmental - RFP'S FOR CEQA ANALYSIS SENT
02/26/2013 Application - REVISED PLANS SUBMITTED
03/04/2013 Project Review Request - SECOND PRR ROUTED, COMMENTS DUE BACK 03/18/2013
03/04/2013 Application - TRACT MAP AND REVISED WQMP SUBMITTED. WQMP ROUTED TO BAGAHI FOR REVIEW.
04/02/2013 Environmental - CEQA CONSULTANT SELECTED
04/04/2013 Letter Sent - INCOMPLETE LTR 2 SENT
05/22/2013 Environmental - FIRST DRAFT MND RECEIVED FOR CITY REVIEW AND COMMENT, COMMENTS DUE BACK JUNE 6, 2013 TO CONSULTANT
06/17/2013 Environmental - SECOND DRAFT MND RECEIVED FOR CITY REVIEW AND COMMENT FROM CONSULTANT
07/12/2013 Environmental - PUBLIC COMMENT PERIOD FOR MND BEGINS
07/15/2013 Environmental - OPR PUBLIC COMMENT PERIOD BEGINS, REVIEW PERIOD ENDS AUGUST 14, 2013
08/06/2013 Letter Sent - ADDITIONAL TRIBAL CONSULTATION LETTERS SENT, 90 DAY CONSULTATION PERIOD ENDS NOVEMBER 4, 2013
08/13/2013 Environmental - END OF MND PUBLIC COMMENT PERIOD
08/20/2013 Letter Sent - SEVEN ADDITIONAL NAHC CONTACTS CONTACTED WITH REQUEST FOR SHORTENED CONSULTATION PERIOD OF 45-DAYS TO SEPTEMBER 20TH
08/20/2013 Other - TRIBAL CONTACTS CONTACTED FOR FOLLOW-UP REGARDING INVITATION TO CONSULT IN COMPLIANCE WITH SB18 REQUIREMENTS
08/22/2013 Planning Commission - CONTINUED
09/05/2013 Planning Commission - APPROVED, CONTINUED FROM 08/22/13
09/25/2013 Other - TRIBAL CONTACTS CONTACTED FOR FOLLOW-UP REGARDING INVITATION TO CONSULT IN COMPLIANCE WITH SB18
11/04/2013 Other - END OF SB18 TRIBAL CONSULTATION PERIOD
11/12/2013 City Council - APPROVED
11/13/2013 Environmental - NOD FILED AT COUNTY RECORDERS OFFICE
11/25/2013 Other - COASTAL CLUP APPLICATION MAILED
11/26/2013 City Council - ORDINANCE SECOND READING, APPROVED
12/10/2013 Other - COASTAL COMMISSION COMMENTS RECEIVED
12/13/2013 Other - COASTAL RESUBMITTAL HAND DELIVERED TO CCC OFFICES
12/20/2013 Other - COASTAL COMMISSION COMMENTS RECEIVED
03/12/2014 Other - CLUP AMENDMENT APPROVED AT COASTAL COMMISISON
04/23/2014 Other - CDP APPLICATION FOR THE PROJECT SUBMITTED TO CALIFORNIA COASTAL COMMISSION
03/02/2017 Application - EXTENSION OF TIME