10/24/2012 |
Application - SUBMITTED |
|
11/21/2012 |
Project Review Request
- PRR ROUTED, COMMENTS DUE BACK |
|
11/21/2012 |
Letter Sent - INCOMPLETE LTR SENT |
|
12/06/2012 |
Project Review Request
- PRR ROUTED TO GENERAL SERVICES REGARDING TRASH SERVICE, COMMENTS DUE BACK 12/21/12 |
|
01/07/2013 |
Application - ADDITIONAL APPLICATION MATERIALS RECEIVED |
|
01/18/2013 |
Other - CORRESPONDENCE WITH APPLICANT, PROJECT SCOPE TO BE REVISED TO 23 UNITS FROM 24 UNITS |
|
01/30/2013 |
Letter Sent - TRIBAL CONSULTATION LETTERS SENT, 90 DAY CONSULTATION PERIOD ENDS APRIL 30, 2013 |
|
02/19/2013 |
Environmental - RFP'S FOR CEQA ANALYSIS SENT |
|
02/26/2013 |
Application - REVISED PLANS SUBMITTED |
|
03/04/2013 |
Project Review Request
- SECOND PRR ROUTED, COMMENTS DUE BACK 03/18/2013 |
|
03/04/2013 |
Application - TRACT MAP AND REVISED WQMP SUBMITTED. WQMP ROUTED TO BAGAHI FOR REVIEW. |
|
04/02/2013 |
Environmental - CEQA CONSULTANT SELECTED |
|
04/04/2013 |
Letter Sent - INCOMPLETE LTR 2 SENT |
|
05/22/2013 |
Environmental - FIRST DRAFT MND RECEIVED FOR CITY REVIEW AND COMMENT, COMMENTS DUE BACK JUNE 6, 2013 TO CONSULTANT |
|
06/17/2013 |
Environmental - SECOND DRAFT MND RECEIVED FOR CITY REVIEW AND COMMENT FROM CONSULTANT |
|
07/12/2013 |
Environmental - PUBLIC COMMENT PERIOD FOR MND BEGINS |
|
07/15/2013 |
Environmental - OPR PUBLIC COMMENT PERIOD BEGINS, REVIEW PERIOD ENDS AUGUST 14, 2013 |
|
08/06/2013 |
Letter Sent - ADDITIONAL TRIBAL CONSULTATION LETTERS SENT, 90 DAY CONSULTATION PERIOD ENDS NOVEMBER 4, 2013 |
|
08/13/2013 |
Environmental - END OF MND PUBLIC COMMENT PERIOD |
|
08/20/2013 |
Letter Sent - SEVEN ADDITIONAL NAHC CONTACTS CONTACTED WITH REQUEST FOR SHORTENED CONSULTATION PERIOD OF 45-DAYS TO SEPTEMBER 20TH |
|
08/20/2013 |
Other - TRIBAL CONTACTS CONTACTED FOR FOLLOW-UP REGARDING INVITATION TO CONSULT IN COMPLIANCE WITH SB18 REQUIREMENTS |
|
|
|
09/25/2013 |
Other - TRIBAL CONTACTS CONTACTED FOR FOLLOW-UP REGARDING INVITATION TO CONSULT IN COMPLIANCE WITH SB18 |
|
11/04/2013 |
Other - END OF SB18 TRIBAL CONSULTATION PERIOD |
|
|
11/13/2013 |
Environmental - NOD FILED AT COUNTY RECORDERS OFFICE |
|
11/25/2013 |
Other - COASTAL CLUP APPLICATION MAILED |
|
11/26/2013 |
City Council
- ORDINANCE SECOND READING, APPROVED |
|
12/10/2013 |
Other - COASTAL COMMISSION COMMENTS RECEIVED |
|
12/13/2013 |
Other - COASTAL RESUBMITTAL HAND DELIVERED TO CCC OFFICES |
|
12/20/2013 |
Other - COASTAL COMMISSION COMMENTS RECEIVED |
|
03/12/2014 |
Other - CLUP AMENDMENT APPROVED AT COASTAL COMMISISON |
|
04/23/2014 |
Other - CDP APPLICATION FOR THE PROJECT SUBMITTED TO CALIFORNIA COASTAL COMMISSION |
|
03/02/2017 |
Application - EXTENSION OF TIME |
|