PA2015-210    Harbor Pointe Senior Living Council District 3
DA2018-006 - Development Agreements
ER2018-001 - Environmental Impact Rep
GP2015-004 - General Plan Amendment
PD2015-005 - Planned Comm Dev Plan Am
SD2015-007 - Site Development Review
UP2015-047 - Use Permit
View Ordinances and Resolutions (Not all projects require a Resolution or Ordinance, or documents may not be available at this time.)
Description: General Plan Amendment, Planned Community Text Amendment, Conditional Use Permit, and Major Site Development Review for a new approximately 85,000-square-foot convalescent and congregate care facility with 120 beds. As proposed, the facility will be developed with one subterranean level with parking and amenities. Three levels of care units and additional amenities will be constructed above grade. The project site is currently developed with an approximate 8,800-square-foot single-story restaurant and supporting surface parking area.
Contact: B. Zdeba - 949-644-3253

Status: APPROVED Applied: 11/23/2015 Follow-up Rev: Approved: 2/12/2019
Final: Effective: 3/19/2019 Expired: Denied:
Pending: Date Withdrawn: Voided:
Date Activity - Status
11/23/2015 Application - SUBMITTED
11/23/2015 Admin Setup -
12/08/2015 Project Review Request - ROUTED TO BUILDING, PUBLIC WORKS/UTILITIES, AND FIRE.
12/23/2015 Project Review Request - RETURNED
12/23/2015 Request for More Info - REQUESTED ADDITIONAL INFORMATION FROM APPLICANT (WQMP, GRADING, ETC.)
01/07/2016 Letter Sent - RFP RELEASED FOR ENVIRONMENTAL CONSULTANT
01/25/2016 Letter Sent - RFP DEADLINE REVISED DUE TO RETURNED MAILINGS
02/12/2016 Other - PROPOSAL RECEIVED AND UNDER REVIEW
03/01/2016 Other - BONTERRA PSOMAS SELECTED AS CEQA CONSULTANT
03/16/2016 Project Review Request - PRELIMINARY WQMP ROUTED FOR REVIEW
04/04/2016 Project Review Request - PRELIMINARY WQMP - CORRECTIONS RECEIVED
04/20/2016 Project Review Request - REVISED PRELIMINARY WQMP ROUTED FOR REVIEW
05/16/2016 Project Review Request - PRELIMINARY WQMP 2ND CORRECTIONS RECEIVED
05/17/2016 Project Review Request - REVISED PRELIMINARY WQMP ROUTED FOR REVIEW
07/22/2016 Environmental - NOTICE OF PREPARATION RELEASED - 30-DAY PERIOD TO CONCLUDE ON AUGUST 22, 2016
05/26/2017 Letter Sent - LETTER SENT TO APPLICANT'S REPRESENTATIVES REGARDING CURRENT STATUS AND NECESSARY ITEMS TO PROCEED
10/13/2017 Application - REVISED PROJECT PLANS SUBMITTED FOR REVIEW.
06/15/2018 Application - WQMP
09/13/2018 Planning Commission - Scheduled
12/06/2018 Planning Commission - VOTED 6-0 TO RECOMMEND THE CITY COUNCIL CERTIFY THE EIR AND APPROVE THE PROJECT
02/12/2019 City Council - VOTED 5-1 TO APPROVE THE PROJECT.
02/26/2019 City Council - SECOND READING SCHEDULED.