11/23/2015 |
Application - SUBMITTED |
|
|
12/08/2015 |
Project Review Request
- ROUTED TO BUILDING, PUBLIC WORKS/UTILITIES, AND FIRE. |
|
12/23/2015 |
Project Review Request
- RETURNED |
|
12/23/2015 |
Request for More Info - REQUESTED ADDITIONAL INFORMATION FROM APPLICANT (WQMP, GRADING, ETC.) |
|
01/07/2016 |
Letter Sent - RFP RELEASED FOR ENVIRONMENTAL CONSULTANT |
|
01/25/2016 |
Letter Sent - RFP DEADLINE REVISED DUE TO RETURNED MAILINGS |
|
02/12/2016 |
Other - PROPOSAL RECEIVED AND UNDER REVIEW |
|
03/01/2016 |
Other - BONTERRA PSOMAS SELECTED AS CEQA CONSULTANT |
|
03/16/2016 |
Project Review Request
- PRELIMINARY WQMP ROUTED FOR REVIEW |
|
04/04/2016 |
Project Review Request
- PRELIMINARY WQMP - CORRECTIONS RECEIVED |
|
04/20/2016 |
Project Review Request
- REVISED PRELIMINARY WQMP ROUTED FOR REVIEW |
|
05/16/2016 |
Project Review Request
- PRELIMINARY WQMP 2ND CORRECTIONS RECEIVED |
|
05/17/2016 |
Project Review Request
- REVISED PRELIMINARY WQMP ROUTED FOR REVIEW |
|
07/22/2016 |
Environmental - NOTICE OF PREPARATION RELEASED - 30-DAY PERIOD TO CONCLUDE ON AUGUST 22, 2016 |
|
05/26/2017 |
Letter Sent - LETTER SENT TO APPLICANT'S REPRESENTATIVES REGARDING CURRENT STATUS AND NECESSARY ITEMS TO PROCEED |
|
10/13/2017 |
Application - REVISED PROJECT PLANS SUBMITTED FOR REVIEW. |
|
06/15/2018 |
Application - WQMP |
|
|
12/06/2018 |
Planning Commission
- VOTED 6-0 TO RECOMMEND THE CITY COUNCIL CERTIFY THE EIR AND APPROVE THE PROJECT |
|
|
|