PA2018-185    VIVANTE SENIOR HOUSING Council District 5
LM2018-004 - Lot Merger
UP2018-019 - Use Permit
GP2018-003 - General Plan Amendment
PC2018-001 - Planned Comm Devlop Plan
SD2018-003 - Site Development Review
DA2018-005 - Development Agreements
ER2016-002 - Environmental Impact Rep
View Ordinances and Resolutions (Not all projects require a Resolution or Ordinance, or documents may not be available at this time.)
Description: The project consists of the demolition of the existing Orange County Museum (approximately 24,000 square feet.) and associated administrative office building (approximately 15,000 square feet) on a 2.91-acre site to accommodate the development of a 184,309-sq-ft, 6-story combination senior housing development (90 residential dwelling units, 126 beds) and memory care facility (9 units, 27 beds).
Contact: M. Nova - 949-644-3249

Status: APPROVED Applied: 8/8/2018 Follow-up Rev: Approved: 8/13/2019
Final: Effective: 10/10/2019 Expired: Denied:
Pending: Date Withdrawn: Voided:
Date Activity - Status
08/08/2018 Application -
08/15/2018 Project Review Request - PRR ROUTED, COMMENTS DUE BACK 09/05/2018
09/06/2018 Letter Sent - INCOMPLETE LTR SENT
09/10/2018 Project Review Request - PRR ROUTED TO FIRE SERVICES, PD, AND MOD, COMMENTS DUE BACK SEPTEMBER 21
09/11/2018 Admin Setup -
09/20/2018 Project Review Request - PRR ROUTED TO UTILITIES, COMMENTS DUE BACK OCTOBER 4
12/21/2018 Application - APPLICATION MATERIALS RESUBMITTED
12/21/2018 Environmental - PLACEWORKS CEQA PROJECT DESCRIPTION SUBMITTED TO CITY
01/29/2019 Project Review Request - PRR ROUTED, COMMENTS DUE BACK 02/13/19
01/31/2019 Environmental - CEQA COMMENTS ON PROJECT DESCRIPTION SENT TO CONSULTANT
02/04/2019 Letter Sent - INCOMPLETE LTR 2 SENT
03/20/2019 Letter Sent - NAHC REQUEST LETTER SENT
04/04/2019 Letter Sent - SB-18 LETTERS SENT, 90-DAY NOTICE PERIOD THROUGH 07/03/19 AB-52 LETTERS SENT, 30-DAY NOTICE PERIOD THROUGH 05/04/19
04/09/2019 Other - REQUEST TO CONSULT RECEIVED PER AB-52
04/16/2019 Application - APPLICATION MATERIALS RESUBMITTED
04/18/2019 Planning Commission - PC STUDY SESSION
04/23/2019 Project Review Request - PRR ROUTED, COMMENTS DUE BACK 05-03-19
05/21/2019 Environmental - SECOND DRAFT ADDENDUM RECEIVED FROM PLACEWORKS
06/05/2019 Application - APPLICATION MATERIALS RESUBMITTED
06/17/2019 Environmental - SECOND DRAFT EIR ADDENDUM COMMENTS PROVIDED TO PLACEWORKS
06/26/2019 Application Complete -
06/28/2019 Other - ALUC APPLICATION SUBMITTED
07/08/2019 Environmental - FINAL EIR ADDENDUM RECIEVED FROM PLACEWORKS
07/18/2019 Planning Commission - PC RECOMMENDED CITY COUNCIL CERTIFICATION OF EIR ADDENDUM AND APPROVAL OF PROJECT
07/18/2019 Other - ALUC APPROVED
08/13/2019 City Council - CITY COUNCIL APPROVED
09/10/2019 City Council - CITY COUNCIL ORDINANCES SECOND READING SCHEDULED